Optional) Base Installation Scenario - Huawei FusionModule1000A Installation Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A:
Table of Contents

Advertisement

FusionModule1000A40 Prefabricated All-in-One Data
Center
Installation Guide
(1) Concrete platform
The minimum cross-sectional area of a concrete platform must be 2900 mm x 1000 mm. The
concrete platforms must be 500 mm higher than the ground to ensure efficient drainage.

2.2.2 (Optional) Base Installation Scenario

Issue 03 (2020-06-09)
Figure 2-1 Concrete platform (unit: mm)
Load-bearing capacity of concrete platforms: meets the requirements of the maximum
weight of a pre-fab. module 25,000 kg and NEBS Zone 3 antiseismic requirements.
Recommended load-bearing capacity calculation: Maximum weight of a pre-fab. module 25,000 kg x 3
(NEBS Zone 3 requires amplitude acceleration 3G) x 1.5 (0.5 times the engineering construction error
and margin)/Effective support contact area (The effective contact area in the concrete platform
installation scenario is 4 x 272 cm
The horizontal error between concrete platforms must be less than 5 mm.
Concrete pads or passages with the load-bearing capacity meeting local civil work
standards can be built on the site outside the concrete platforms for access and servicing.
Build concrete platforms on the selected installation site.
Copyright © Huawei Technologies Co., Ltd.
(2) Ground
2
.)
2 Site Requirements
(3) Angle steel
3