FusionModule1000A40 Prefabricated All-in-One Data
Center
Installation Guide
If the battery is damaged or leaks, contact Huawei technical support to replace the battery.
Step 3 Connect the battery cables to the reserved power cable terminals.
Figure 8-24 Battery position
Figure 8-25 Connecting battery cables
Do not connect the red positive cable until power-on commissioning.
Ensure that battery cables for the extinguishant control panel are connected to correct
polarities.
Step 4 Close the door of the fire control panel.
----End