FusionModule1000A40 Prefabricated All-in-One Data
Center
Installation Guide
Figure 8-1 Installing mounting ears
Step 3 Push the battery pack onto the guide rails, and secure the battery pack to the cabinet rack rails
using mounting ears and screws.
Figure 8-2 Installing a battery pack
Step 4 Install other battery packs in the same way.
Step 5 Connect cables between battery packs based on the battery pack wiring diagram.
----End
Follow-up Procedure
Verify the battery pack cable connections. Ensure that the battery pack quantity and cable
connections comply with the design and the cables or copper bars are reliably installed.