Cw-80T & Cw-80T-Twin Supply Outlet Ducts - Seeley Climate Wizard CW-80 Installation & Operation Manual

Table of Contents

Advertisement

INSTALLATION cont.
CW-80T & CW-80T-TWIN Supply Outlet
Ducts
The outlet duct(s) is to be unscrewed from the transport
pallets and then lifted up and positioned on top of CW-
80T using the lifting points already installed. A crane with
a spreader bar is necessary for this.
Position the duct(s) centrally to the cooler and make sure
the flanges of the duct(s) are directly over the foam seal
(on top of the cooler as installed by the factory) and that
the mounting holes are aligned.
ILL2299-A
Fasten the outlet duct(s) into position using M8 screw
assembly B.
M8 SCREW
ASSEMBLY "A"
M8 FLAT
WASHER
(LARGE O.D.)
16 |
CW-80 Container Cooler 866600CE-B
ILL2299-A
ILL2300-A
M8 SCREW
M8 SCREW
ASSEMBLY
ASSEMBLY "B"
"B"
M8 SPRING
WASHER
M8 SCREW
ILL2301-A
ILL2221-A
The CW-80T-TWIN supply Outlet Ducts have allocations
made to fasten together in the centre area to prevent
vibration.
Fasten using 4 off M8 screw assembly B.
It is expected that the supplied lifting points can remain
in their as-supplied position protruding inside into the
customers inlet ducting. In the case that the lifting points
cause an interference, they can be readily disassembled
and then reassembled upside down after the Outlet
Duct(s) is craned into position and that the Outlet Duct(s)
has been bolted Down.
By re-fitting the lifting points (upside down) will ensure
that the holes are covered up and the Duct(s) is airtight.
ILL2300-A
ILL2366-B
ILL236
ILL2367-A
ILL