INSTALLATION

MOUNTING / SUPPORT

Roofstands, accommodating 0-10 roof pitches, are available for
order via Seeley International. See Optional Components List.

SUPPLY AIR DUCT PREPARATION

The cooler is designed to be mounted on a supply air duct with
outside dimensions of 530 x 530mm (20 7/8" x 20 7/8") and
1.0mm (20 gauge) thick. The duct must have a raw edge or safe
edge at the top. Do not fold in a flange as this may interfere with
the transition and/or the weatherseal
ILL2774-A
For installations which require the cooler power and
communications cables to pass down the inside of the supply
duct, cut a 50mm (2") diameter cable exit hole in the side of the
duct.
Fit the rubber cable grommet suppled in the installation kit to
protect the cables from the raw cut edge.
Locate the hole below the roof line and so the cables will not
interfere with the operation of the weatherseal.
ILL3368-A
ILL1646-A

PREPARING THE TRANSITION

Locate the supply duct transition assembly in installation kit.
Temporarily remove both weatherseal flaps as shown.
Fit the transition onto the supply duct, ensuring that it is
orientated correctly, as shown below.
Secure the transition to the supply duct using 6 (six) of the
supplied fasteners. There are 2 pilot holes on each side and a
single hole on the front and rear (centre) of the transition.
COOLER
FRONT
859741-L CW3 INSTALLATION MANUAL
ILL2775-A
COOLER
SIDE
ILL2776-A