To start a verification proceed as follows:
Maintenance
Verification
Calibration
Simulation
Set Time 01.01.05 16:30:00
Verification
- Turn valve to EMPTY
- Replace Measuring Unit
with Test Unit
- Turn valve to LINE
<Enter> to continue
Verification
Setpoint
5.00 FNU
<Enter> to continue
Verification
- Actual Value
x.xx FNU
- Setpoint
5.00 FNU
- Deviation
<Enter> to save
Error message: Deviation too big
If the value is lower or higher than ±10%, proceed as follows:
 Check the sample temperature and if necessary adjust it.
 Clean the measuring chamber.
1 Navigate to menu <Maintenance>/
3.1
<Verification> and press [Enter].
2 Stop sample flow.
3 Empty measuring chamber by turn-
ing the manual 5/4 valve to EMPTY.
3.1.5
EMPTY
ZERO
4 Open the measuring chamber.
5 Insert the test unit into the mea-
surement chamber.
6 Turn the manual 5/4 valve to LINE
and start sample flow.
7 Press [Enter].
3.1.5
 Setpoint is displayed.
8 Press [Enter].
9 Enter the setpoint printed on the la-
bel of the test unit with the [
or [
10 Press [Enter] to confirm.
The verification is running now.
3.1.5
If the deviation is within ± 10%, press
[Enter] to save the value.
x.xx%