Cisco cBR Series Hardware Installation Manual page 238

Converged broadband routers
Hide thumbs Also See for cBR Series:
Table of Contents

Advertisement

Removing the Downstream PHY Module in the Interface Line Card
Required Tools and Equipment
• ESD-preventive wrist strap
• T10 Torx-blade screwdriver
• Replacement line card or line card blank
• Antistatic Bag or mat
Step 1
Loosen the retaining screws (two in the front and one in the rear) using a T10 Torx-blade torque driver.
Step 2
Grasp the Downstream PHY module by its sides.
Step 3
Lift the Downstream PHY module off the cLGA connector guide pins and the rear guide pins on the line card.
Figure 151: Lift the Downstream PHY module
1
2
Ensure that the Downstream PHY module is held horizontal when it is lifted off the guide pins, to prevent
Note
damage to the cLGA connector surface.
Step 4
Place the removed Downstream PHY module in an antistatic bag.
What to do next
Replace the Downstream PHY
Cisco Converged Broadband Routers Hardware Installation Guide
230
Downstream PHY module
Captive screws
module.
Maintaining the PHY Modules in the Cisco cBR Chassis
3
Guide pins