Distribute the First Bag of Developer
Connect the power supply cord and switch the
main power switch on.
The main motor switches on and distributes the
developer evenly inside the development unit.
Wait about 22 seconds.
Turn the operation switch off, then turn the main
power switch off.
Slide 56
After installing the first bag, you must turn on the machine to distribute the
developer evenly inside the development unit.
If you do not do this, there is no space for you to add the second bag.
When the machine distributes the developer, the paddle roller moves developer
from the front of the unit to the inside of the development unit, and this makes
room to add the second bag.