5 FUNCTIONAL TESTS (FACTORY SETTINGS)
5.4 PHASE-TO-PHASE ZONE REACH TESTING
1.
Protection Settings:
Z1DISTANCE
(101)
Z1PHASE = YES
(104)
Z1GROUND = NO
Z2DISTANCE
(201)
Z2PHASE = NO
(204)
Z2GROUND = NO
Z3DISTANCE
(301)
Z3PHASE = NO
(304)
Z3GRND = NO
Z4DISTANCE
(401)
Z4PHASE = NO
(405)
Z4GRND = NO
OVERCURRNT
(601)
50 = NO
(605)
50G = NO
(610)
51G = NO
OS BLOCKING
(1603)
BLOCKWHAT = 3 (BLKNONE)
2.
Connect the relay as shown in Figure 5–1: PHASE-TO-PHASE TEST CONNECTIONS on page 5–6 for the appropri-
ate phases under test. Set the relay to test mode 30 (Any Zone 1 Phase). The LUI displays: ANY Z1 PHASE ON
Set the voltage inputs as follows: VA: 67 V rms ∠0°, VB: 67 V rms ∠–120°, VC: 67 V rms ∠+120°.
3.
4.
Set the phase angle of the fault current I
phase angle is 180° out of phase with the line to which it is shorted.
∠I DEGREES
VOLTS RMS
–25
51 to 57
–55
59 to 66
–85
51 to 57
Reference only
5.
Set the fault current to 10.0 (2.0) amps rms. Reduce the voltage of the faulted phases and check that the A1 contact
closes when the voltages are within the limits shown above.
6.
Reduce the fault current to zero. Note that the trip target indication concurs with the fault. For example, an AB fault is
displayed as follows: TRIP AB Z1 "DIST", where "DIST" is the displayed target.
7.
Repeat the test for phase BC and CA faults.
1.
Protection Setting:
Z1DISTANCE
(101)
Z1PHASE = NO
(104)
Z1GROUND = NO
Z2DISTANCE
(201)
Z2PHASE = YES
(204)
Z2GROUND = NO
(209)
Z2P_TIME = 0.1
(210)
Z2G_TIME = 0.1
GE Power Management
to the phase-angle value listed in the table below. Note that the leading
op
DISPLAYED TARGET
82 to 88
ALPS Advanced Line Protection System
5.4 PHASE-TO-PHASE ZONE REACH TESTING
5.4.1 T16 – ZONE 1 PHASE REACH, M1 FAULTS
5.4.2 T17 – ZONE 2 PHASE REACH, M2 FAULTS
5
5-13

Advertisement

Table of Contents
loading

Table of Contents