Outrigger Control Valve
31200079
6. Remove the two (2) nuts (Item 13), lockwashers (Item 12), and
capscrews (Item 5) securing each valve section to the control panel
(Item 11). Remove the outrigger valve sections.
(Ref. Fig. 10-11) The following procedure describes installation of the
outrigger control valves.
1. Secure the two (2) outrigger control valves (Item 4) to the frame tilt
control valve (Item 6) with three (3) tie rods (Item 3). Install
lockwashers (Items 2 and 7) and nuts (Items 1 and 8) on each end of
both tie rods.
2. Install each outrigger control valve on the control panel (Item 11) with
two (2) capscrews (Item 5), lockwashers (Item 12), and nuts (Item 13).
Torque the nuts to 50 in-lbs.
3. Install the hydraulic hoses (Item 10) on the connectors (Item 9) on the
bottom of each control valve. For final tightening, torque the hose
swivel nuts to 130–150 in-lbs.
4. Install the rear cover (Item 14) on the operators compartment with four
(4) flatwashers (Item 15) and screws (Item 16). Torque the screws to
96 in-lbs.
Outriggers
10-15