Mounting and installation FC2080
6

Installing the carrier (19", power supply)

6.9 Installing the carrier (19", power supply)
288 | 354
Building Technologies
Fire Safety
The carrier (19", power supply) FHA2022-A1 is installed on the side of the cabinet.
The installation position can be determined depending on the arrangement of the
other components and the battery tray. When installing two carriers (19", power
supply), note that the installation position of the top carrier is as high as possible.
Enclosed accessories
4 threaded screws M 6 x 12
Prerequisites
Main switch installed
Socket installed, if required
Third power supply (150 W) installed, if required
Note the installation position of the carrier (19", power supply). When installing
two carriers (19", power supply), the top carrier must be installed as high as
possible. If the carrier is installed too low, there will not be enough room to install
a second carrier (19", power supply).
Only one main switch (accessory for housing FH2080-AA) need be installed per
fire control panel FC2080. When installing two carriers (19", power supply), install
the main switch preferably on the bottom carrier (mains supply cable).