Siemens FS20 Mounting & Installation page 290

Fire detection system
Table of Contents

Advertisement

Mounting and installation FC2080
6
Installing the carrier (19", power supply)
290 | 354
Building Technologies
Fire Safety
Installation positions for two carriers (19", power supply)
When installing two carriers (19", power supply), the carriers should be installed as
high as possible to keep sufficient space for the battery trays.
A
1
Top mounting point for first carrier
2
Bottom mounting point for first carrier
B
1
Top mounting point for second carrier
2
Bottom mounting point for second carrier
Installation positions for one carrier (19", power supply)
When using just one carrier (19", power supply), it can basically be positioned
anywhere. The mounting points (C) serve only as an example.
C
1
Top mounting point
2
Bottom mounting point
1. Install the prepared carrier (19", power supply) (1) on the lateral crossbars (2)
with four fastening screws (4) and cage nuts.
2. Wire up the carrier (19", power supply) according to the following pin
assignments.
008851_s_en_--
2016-01-27