Siemens FS20 Mounting & Installation page 60

Fire detection system
Table of Contents

Advertisement

Mounting and installation of the compact control panels
5
Mounting procedure
60 | 354
Building Technologies
Fire Safety
8. Fit the cover cap(s) and screw into place.
9. Secure the installation plate on the outside of the control panel housing such
that it is clearly legible.
Add the site number 'No.:' and the commissioning date 'Date:' during
commissioning in accordance with EN 54-2.
a The station is then ready for commissioning.
FC2020
85...265VAC
EN54-2 / (PSU:EN54-4)
Prod. Date:
Figure 25: Sample installation plate
Siemens Switzerland Ltd
Fire Safety & Security Products
CH-6301 Zug
90VAC
G209076
008851_s_en_--
2016-01-27

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents