7.14. Check sheet of Point to Point Construction

Check operation of the WT (Master/Slave) using the check sheet below.
Test procedure
(A) LED operation test
-
Remove the AC adapter (to turn off the power) and make sure that all the LEDs go out.
Insert the AC adapter (to turn on the power) and check the states of the LEDs.
-
(B) Loopback test between the WT and the WT adapter
Press the TEST switch on the WT adapter and make sure that the ETHER LED goes
-
out.
-
Remove the cable from the WT adapter's PC port and make sure that the ETHER LED
goes out.
(C) Receive level
Connect the WT Local Management Tool to the WT and measure the receive level.
-
WT
Serial number
Test type
Test condition
LED
operation
Remove the AC
test
adapter.
Insert
adapter.
Loopback
test
between WT and
WT adapter
Press the TEST
switch on the WT
adapter.
Receive level
Remove
cable from the
WT adapter's PC
port.
Table 7-1 Check sheet
Confirm that the POW LED on the WT adapter goes out.
Confirm that the ETHER LED on the WT adapter goes
out.
Confirm that the ALM LED on the WT adapter goes out.
the
AC
Confirm that the POW LED on the WT adapter lights
green.
Confirm that the ETHER LED on the WT adapter flashes
green.
Confirm that the ALM LED on the WT adapter flashes at
1-second intervals and then goes out.
Confirm that the ETHER LED on the WT adapter goes
out.
Confirm that the ETHER LED on the WT adapter goes
out.
the
Connect the WT Local Management Tool to the WT and
measure the receive level.
Test date
Check item
7-149
Pass/fail Measured value
-
-
-
-
dBm