Commissioning (hardware)

5.1

Overview

Requirements
The following requirements must be satisfied for the first commissioning of the
SIMOTION D410‑2:
● Your system with SIMOTION D410‑2 has been installed and wired.
● Your PG/PC is connected to the SIMOTION D410‑2 via the PROFIBUS DP, Ethernet, or
PROFINET (D410-2 DP/PN only) interface.
Commissioning steps
Commissioning the hardware involves the following steps:
1. Inserting the CompactFlash card (Page 80)
2. Checking the system (Page 82)
3. Switching on the power supply (Page 83).
Additional references
For information on installing/mounting and commissioning the SINAMICS S120 components,
refer to the
SIMOTION D410-2
Commissioning and Hardware Installation Manual, 01/2015
SINAMICS S120 Commissioning Manual.