4. Switch off all main line switches of the AC section.
Caution – There is an electrical hazard if the power cords are not disconnected. All power
cords must be disconnected to completely remove power from the server.
4.4.2

Powering the Server On

Two power-on procedures are available.
From the Operator Panel
Follow the power-on procedure below.
1. Confirm that the mode switch on the operator panel is set to the Service position.
2. Confirm that the POWER LED and CHECK LED on the operator panel are off and
the XSCF LED on the operator panel is lit.
3. If the XSCF LED is off, switch on all the system main line switches.
4. Press and hold down (for less than four seconds) the POWER switch on the operator
panel.
5. Check the POWER LED.
When it becomes lit, the power-on procedure is completed.
If the state of any of the LEDs is different from the above, see
Display" on page
From the Maintenance Terminal
Follow the power-on procedure below using the XSCF maintenance functions.
1. Make sure that the server has enough power supply units to run the desired
configuration.
2. Switch on all main line switches of the AC section.
3. Make sure the XSCF Unit Ready LED is lit.
4-22
SPARC Enterprise M8000/M9000 Servers Service Manual • October 2012
2-30.
Section 2.7, "LED Error

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sparc enterprise m9000

Table of Contents