Cold Replacement - Fujitsu SPARC Enterprise M8000 Service Manual

Oracle
Hide thumbs Also See for SPARC Enterprise M8000:
Table of Contents

Advertisement

11.3

Cold Replacement

In cold replacement, none of the replacement work is performed with the maintenance menu
from a terminal connected to XSCF.
The procedure is as follows.
1. Unlock and open a door of the server. (See
Caution – Before touching a FRU or dummy (filler) unit, see
Precautions" on page 1-9
result in serious damage to operating domains.
2. Change the mode switch setting on the operator panel from Locked to Service.
Note – When the maintenance work is completed, be sure to confirm the mode switch
setting and return the switch to Locked.
3. Use one of the following methods to stop (power off) all domains at once.
The OS shutdown processing is executed for all the domains, and then the power-off
processing is executed.
4. Confirm that the power-off processing is completed by confirming that the POWER
LED (green) on the operator panel is off.
5. Switch off all main line switches for the AC section (ACS) in the power supply
system. (See
Note – If the optional three-phase 200 VAC input power supply unit is installed, the main
line switches are located on the three-phase ACS.
Note – If the dual power feed option is installed, switch off the main line switches for both
power supply units.
11-12
SPARC Enterprise M8000/M9000 Servers Service Manual • October 2012
and be sure to wear the antistatic wrist strap. Failure to do so might
Press and hold down the POWER switch on the operator panel for at least four
seconds.
From a console that is connected to XSCF, log in to XSCF, and execute the
poweroff -a command.
Section 4.5.3, "Main Line Switch Locations" on page
Chapter
5)
Section 1.4, "Antistatic
4-30)