12
|
Commissioning
Possible actuator test runs
To perform a current sensor phase check
Installer reference guide
218
1 Set the user permission level to Installer. See
user permission
level" [
2 Go to [A.2]: Commissioning > Actuator test run.
3 Select a test from the list. Example: Pump.
4 Select OK to confirm.
Result: The actuator test run starts. It stops automatically when
ready (±30 min).
To stop the test run manually:
1 In the menu, go to Stop test run.
2 Select OK to confirm.
▪
Backup heater 1 test (3 kW capacity, only available when no current sensors
are used)
▪
Backup heater 2 test (6 kW capacity, only available when no current sensors
are used)
▪
Pump test
INFORMATION
Make sure that all air is purged before executing the test run. Also avoid disturbances
in the water circuit during the test run.
▪
Shut off valve test
▪
Diverter valve test (3-way valve for switching between space heating and
tank heating)
▪
Bivalent signal test
▪
Alarm output test
▪
C/H signal test
▪
DHW pump test
▪
Backup heater phase 1 test (3 kW capacity, only available when current
sensors are used)
▪
Backup heater phase 2 test (3 kW capacity, only available when current
sensors are used)
▪
Backup heater phase 3 test (3 kW capacity, only available when current
sensors are used)
▪
Water loop valve test
To make sure that the current sensors measure the current of the correct phase,
perform a current sensor phase check. This can be done using the backup heater
actuator tests.
Note: Make sure that Power
sensor ([4‑08]=3). See
1 Set the user permission level to Installer. See
user permission
level" [
4
139].
consumption
"Power consumption
control" [
4
139].
"To change the
control is set to Current
4
200].
"To change the
EWSAH/X06UD
Daikin Altherma 3 WS
4P675765-1 – 2022.04
—
—
—