Power initialisation
Fan unit test
....................................................................................................................................................................................................................................
Overview
Procedure
....................................................................................................................................................................................................................................
365-374-074
Issue a, April 2002
This test clarifies the correct working of the fan unit in the
™
LambdaUnite
MultiService Switch (MSS) subrack. The test should
be carried out for each installed NE.
Proceed as follows to test the correct functionality of the fan
unit:
............................................................................................................................................................
Control the status indication on the faceplate of the fan unit.
1
Result:
On the fan unit only the PWR ON LED should be lit.
............................................................................................................................................................
2
Check that
•
all fans of the unit are running
•
the air flow direction is from bottom to top.
E
S
N D
O F
T E P S
.........................................................................................................................................................................................................................................................
Lucent Technologies
Powering, circuit pack installation, and NE software
download
5 - 7