Power Wiring (External Battery - Pdp) - Lucent Technologies LambdaUnite MSS Installation Manual

Multiservice switch
Table of Contents

Advertisement

Power and ground cable installation

Power wiring (External battery - PDP)

....................................................................................................................................................................................................................................
Before you begin
....................................................................................................................................................................................................................................
365-374-074
Issue a, April 2002
Before connecting any power cables be sure that all circuit breakers
which are located in the external Battery Distribution and Fuse Bay
(BDFB) and at the rear side of the subracks (on the PIs) are in the
OFF
position!
Depending on the length the following power input cables should be
Cabling
used:
Power input cable 25 m [82.021 ft] — CC848827457
Power input cable 16 m [52.493 ft] — CC848827499
Power input cable 8 m [26.247 ft] — CC848827481
Power input cable 5 m [16.404 ft] — CC848827473.
Figure 4-2 PDP connection (power input cables)
+DC (rtn)
(A+B)
1
*
Legend:
1
+DC (red, return)
2
-DC (blue)
Lucent Technologies
-DC
(A+B)
2
System cabling and final assembly
4 - 5