Job Aid: Replacing the SAMP on the Avaya S8510
Server
!
Important:
Always check the Avaya Support Website for Product Support Notices at
Important:
support.avaya.com/japple/css/
japple?PAGE=ProductArea&temp.productID=162774.
This Job Aid contains the procedures to replace the Server Availability Management
Processor™ (SAMP) remote maintenance board on the Avaya S8510 Server.

Required materials

Hardware and tools

Verify that you have the following equipment and tools on site:
S8510 SAMP Board, Material ID 700451198
Services laptop and crossover cable
#2 Phillips (cross-point) screwdriver
Electrostatic wrist ground strap and mat
Key to front bezel
Note:
The server ships with the front bezel unlocked and the keys taped inside it. The
Note:
customer decides whether to lock the front bezel or not. When you are finished
with the replacement procedure, please leave the server's front bezel as you
found it.

Additional information

The following Avaya S8510 documents might be helpful:
Installing the Avaya S8510 Server and its Components (03-602918)