Replacing Components
6. Place the new water pump on the wall and secure it in place with four screws.
7. Connect the power wires to the water pump. Note that this is a DC powdered
pump and the wires must be placed on the correct terminals. Connect the red
wire (positive) to the terminal with the red marking, and connect the blue wire
(ground) to the other terminal.
8. Connect the water pump outlet hose to the inlet of the "Y" fitting (on the brewer side
of the wall.
9. Connect the water pump inlet hose to the fitting on top of the water tank.
10. Test the machine to make certain everything is functioning properly.
11. Install the top panel and the rear panel onto the machine.