Figure 11: Shelf Brackets; Figure 12: U Numbering Above Shelf - Mellanox Technologies MIS5300 Hardware Installation Manual

324-port infiniband qdr switchx switch platform
Table of Contents

Advertisement

InfiniBand Switch Platform Hardware User Manual
7. Insert three caged nuts into the rack for each of the four shelf brackets (the 2 brackets
that are adjustable and the 2 that are fixed). Make sure that the caged nuts are all at
the same height on the vertical supports.
8. Insert 4 caged nuts (two on right and 2 on the left of the spine side) for the bottom
filler panel.
9. Put the Shelf into the rack and twist the shelf into place. Make sure the spine side of
the shelf is closest to the rack doors. See Figure 11 to identify the spine side of the
shelf.
10. Install and tighten the 12 M6 bolts into the caged nuts.
The spine side of
the shelf has
two slots for the
extension
Adjustable shelf
brackets
11. Tighten the 16 hex head bolts on the adjustable brackets.
Mellanox Technologies

Figure 11: Shelf Brackets

Figure 12: U Numbering Above Shelf

3
2
1
2
1
The first cage nut
on the spine side
goes here. The
rest of the caged
nuts go every 4 U
units up from
here.
Top of
Shelf
27