Rev 1.2
Install 8 cage nuts in the desired 1U slots of the rack: 4 cage nuts in the non-extractable side
Step 3.
and 4 cage nuts in the extractable side. Note that while each rack U (unit) consists of three
holes, the cage nut should be installed vertically with its ears engaging the top and bottom holes
only.
While your installation partner is supporting the system's weight, perform Steps 4, 5 and 6:
Mount the system into the rack enclosure and attach the brackets installed on the system to the
Step 4.
rack's posts. Secure the brackets to the rack's posts by inserting four M6 screws in the desig-
nated cage nuts. See Figure 10. Do not tighten the screws yet.
Slide the two blades into the left and right rails, and adjust them to fit your rack's depth. Use
Step 5.
four M6 screws (D) to fix the blades into the rack. Do not tighten the screws yet.
18
Mellanox Technologies
Figure 9: Attaching the Brackets to the Chassis
Figure 10: Attaching the Brackets to the Rack
Installation