Installation Procedure - Mellanox Technologies MIS5300 Hardware Installation Manual

324-port infiniband qdr switchx switch platform
Table of Contents

Advertisement

InfiniBand Switch Platform Hardware User Manual
2. Plug the other end of the wrist strap to a valid ground. Make sure that this is a tight
fit.
1.6.3

Installation Procedure

1.6.3.1 Requirements
You will need:
• #2 phillips screwdriver
• a fork lift
• measuring tape
1.6.3.2 Installation and Cable Management Kit Parts
Parts included in the installation kit:
- 1 shelf with brackets pre-installed
- 1 left side upper bracket offset
- 2 lock down bars
- 8 lock washers for the upper brackets to
vertical support
- 10 hex head bolts – 8 for the upper
brackets and 2 for the shelf extension
Mellanox Technologies
Installing the chassis will be a lot easier if you can remove the sides of the rack.
You will need a fork lift, to move and insert the chassis into the rack.
• #3 phillips screwdriver
• a grounding lug
• ground wire of sufficient length and gauge to properly ground the
chassis
The installation will be much easier with a power screwdriver.
It is recommended to use AWG6 or 4mm diameter wire for grounding purposes.
It is recommended to have at least two people for the duration of the installation proce-
dure. Use a mechanical lift to raise this chassis. If not, use enough manpower to ensure
the safety and wellbeing of all of the people involved in the installation.
- 1 shelf extension
- 1 right side upper bracket offset
- 2 upper bracket washers
- 1 nut Size M-6 for ground post
- 26 caged nuts 12 for the shelf and 8 for the
chassis faceplate and 6 for the filler panels
18