Electro Industries Shark 100 Installation & Operation Manual page 59

Low cost, high performance multifunction electricity meter
Hide thumbs Also See for Shark 100:
Table of Contents

Advertisement

5.2.2: Shark Profile Settings
Scaling (CT, PT Ratios and System Wiring)
CT Numerator (Primary):
CT Denominator (Secondary):
CT Multiplier:
CT Fullscale:
Calculation Based on Selections
PT Numerator (Primary):
PT Denominator (Secondary):
PT Multiplier:
PT Fullscale:
Calculation Based on Selections
System Wiring:
Number of Phases: One, Two or Three
NOTE:
VOLTS FULL SCALE = PT Numerator x PT Multiplier
WARNING:
You must specify Primary and Secondary Voltage in Full Scale. Do not use ratios!
The PT Denominator should be the Secondary Voltage level.
Example:
A 14400/120 PT would be entered as:
PT Num:
PT Denom:
Multiplier:
This example would display a 14.40kV.
Example CT Settings:
200/5 Amps:
800/5 Amps:
2,000/5 Amps:
10,000/5 Amps:
Example PT Settings:
277/277 Volts
14,400/120 Volts:
138,000/69 Volts:
345,000/115 Volts:
345,000/69 Volts:
.
NOTE: Settings are the same for Wye and Delta configurations.
e
Electro Industries/GaugeTech
1440
120
10
Set the Ct-n value for 200, Ct-Multiplier value for 1.
Set the Ct-n value for 800, Ct-Multiplier value for 1.
Set the Ct-n value for 2000, Ct-Multiplier value for 1.
Set the Ct-n value for 1000, Ct-Multiplier value for 10.
Pt-n value is 277, Pt-d value is 277, Pt-Multiplier is 1.
Pt-n value is 1440, Pt-d value is 120, Pt-Multiplier value is 10.
Pt-n value is 1380, Pt-d value is 69, Pt-Multipier value is 100.
Pt-n value is 3470, Pt-d value is 115, Pt-Multiplier value is 100
Pt-n value is 345, Pt-d value is 69, Pt-Multiplier value is 1000.
Doc #: E145701
5-9