2. Press the rail against the side of the chassis and slide toward the rear of the server
to snap and lock the rail into place.
Figure 4-4: Attaching a server rail to the chassis
IMPORTANT: Be sure that the first rail is firmly anchored to the chassis before attaching
the second rail.
3. Repeat steps 1 and 2 to secure the second rail to the server.
Installing the Spring-Load Rack Rail Assembly in the Rack
The spring-load rack rail assembly consists of a fixed outer rail and a sliding inner
rail. The two rails are shipped as an assembly and do not require additional
preparation.
To install the spring-load rack rail assembly in the rack:
1. From the front of the rack, identify the rack holes on the outside of the front of
the rack that you marked with the template.
NOTE: Use either spring-load rail on either side of the rack. Be sure that the inner rail in
the assembly slides toward the front of the rack.
HP ProLiant ML370 Generation 3 Server Setup and Installation Guide
Installing the Rack Server
4-7