ProKiln GAC400 PROBE GAS SAMPLING SYSTEM | OI/GAC400-EN REV. A
... 6 Installation

Installing the probe

How to lift the probe
1
2
1
2
1 Crane shackle point 1000 kg
Figure 38: How to lift the probe
Lifting instructions
Use only the included crane shackles for lifting.
Weight
1200 kg
Note
Figure 38 is shown without flange shutter – to be installed on kiln wall prior to retractor/probe.
Figure 38 is shown with transport legs front and back (To be removed after usage/install).
2 Transport legs – Remove after installation
1
1
2
1
2