ABB ProKiln GAC400 Operating Instruction page 46

Probe gas sampling system
Table of Contents

Advertisement

46
ProKiln GAC400 PROBE GAS SAMPLING SYSTEM | OI/GAC400-EN REV. A
... 6 Installation
... Installing the probe
How to install the probe
1
Figure 40: Standard 3 m probe, shown with insertion flange / pipe *
1 Typical install area
2 No install in bottom 50 % of kiln
3 No install in top 25 % of kiln
4 Platform floor
5 Typical platform length 6500 mm [256 in]
6 Backend install flange (floor or roof based)
7 ASME B16.5 Slip On Welding Flange - Kiln center lineass 150 8" *
8 Install flange / pipe to be welded to kiln foot wall
9 Installation flange / pipe 8" *
* Customer supply
6
4
3
2
Probe view from top
5052 [199 in]
5
q
r
0 Min. kiln center line height: 1200 mm [47 in]
k Max. kiln center line height: 1600 mm [63 in]
l Typical Platform width: 2000 mm [79 in]
m Kiln center line
n Kiln sealing
o Angle to kiln center line: 45° (-0° +30°)
p Insertion pipe 8" Sch40 (length to be cut flush with kiln inlet lining) *
q Kiln foot wall
r Example of distance to kiln sealing -should be as short as possible (here:
1000 mm [39 in])
7
9
8
j
k
4
l
o
p
n
m
F00712

Advertisement

Table of Contents
loading

Table of Contents