14 Mechanical installation

Installing the FDPI-02 onto the control unit

WARNING!
Obey the safety instructions of the drive. If you ignore them, injury or
death, or damage to the equipment can occur. If you are not a qualified
electrical professional, do not do installation, commissioning or
maintenance work.
1.
Stop the drive and do the Electrical safety precautions in the drive safety
instructions before you start the work.
2.
On the FDPI-02 interface unit, move the slide for the chassis screw to the right.
3.
Insert the interface unit into its designated option slot on the control unit (usually
the option slot nearest to the panel bus connector of the control unit).
4.
Fasten the unit with two screws to a torque of 0.8 N·m (7 lbf·in).
Note: Tighten the grounding screw tight enough to ensure proper grounding. For its
location, see the following figures.
3
1
The screw on the lower left corner provides grounding of the bus cable shield connected
to the unit.