ProKiln GAC400 PROBE GAS SAMPLING SYSTEM | OI/GAC400-EN REV. A
Connect the internal electrical lines
Proceed as follows to connect internal electric lines with all
cables according to flammability acc. EN60332-1-2/-2-2, VW1,
FT1:
1. Turn off the general power
2. Turn off the UPS power supply
3. On the control cabinet: Turn off the main power switch.
4. On the control cabinet: Turn off the UPS power switch.
5. Install internal lines in accordance with the electrical
connection plan. For an overview see .
This applies to:
•
230/400 V AC cable to the probe cooling.
•
24 VDC cable to the probe cooling system
•
ProfiNet® shielded bus cable from to the probe
cooling system
•
230/400 VAC cable between water and cooler panel
for heat exchanger fan motor
•
230 VAC cable to probe retractor for brake probe
•
230 VAC cable to the retractor unit heating
•
24 VDC cable for safety installations
•
24 VDC cable to the retractor unit
•
ProfiNet® bus cable from to the retractor
Neighbouring metallic parts such as gratings, fences,
railings must also be grounded.
6. 230/400 VAC shielded cable from the Control Cabinet to
the Retractor motor.
•
Shielded motor cable: Connect the shield directly to
the shield terminal
converter
, not to the cable gland.
1
Run the cable separately in the control cabinet, not
together with the other lines in the cable duct.
Remove terminal blocks.
Connect to motor.
1
1 Frequency converter
Figure 45: Motor cable shield connection
2
below the frequency
2
2 Shield terminal
Requirements
•
See the electrical connection plan on page
•
Finalize all internal probe gas sampling system cable
connections before connecting external cable connections
and power supply
1
53