ABB ProKiln GAC400 Operating Instruction page 24

Probe gas sampling system
Table of Contents

Advertisement

24
ProKiln GAC400 PROBE GAS SAMPLING SYSTEM | OI/GAC400-EN REV. A
... 3 Design and function
... Components
Cooling water circuit regulation
The open cooling-water circuit must be connected to a potable
water outlet (requirements: see Installing the water system and
cooling panel on page 48). The circulation pump transports at
least 6 m³/h (1585 gal US/h) through the probe cooling jacket.
The resistance thermometer is installed in the cooling water
tank and signals to the water temperature controller.
The water flows through the heat exchanger where a fan is
operated to control the required cooling of the water based on
the water tank temperature. The flow rate is monitored as the
water returns from the probe in order to validate the actual flow
which has been cooling the probe. Monitoring is performed on
the HMI on the control cabinet.
Requirements for the water supply
The water supply must meet the following minimum
requirements:
Category
Requirement
Consumption
0 to 2 m³/year (0 to 528.35 gal US/year)
Quality
Potable water (do not use anti-corrosive), do not use
demineralized water
Ambient temp.
Glycol as anti-freeze. Anti-freeze with anti-corrosive
below 0 °C (32 °F)
additive is not permitted.
Option for water tank heater
Water panel cabinet
The figure below shows the water panel cabinet:
1
2
3
Figure 9: Water panel cabinet
Pos. Component
1
Probe cooling On/Off
2
Breaker for water pump
3
Breaker for Cooling fan 1
4
Breaker for Cooling fan 2
5
Breaker for Tank Heater
4
5
Function
Disconnects the power supply to the
water and cooling system
Turns off water pump
Turns off fan 1
Turns off fan 2
Turns of Tank Heater (optional but
electrically prepared)