To execute test 2 with maximum debug output repeatedly until a Ctrl-c is
entered:
pv -t2 -v9 0
The results on a good system, with the trigger out and break in SMBs
connected, should similar to the following.
U>pv 1
Testing: HPE8130A Series Emulation System
Test
1: Powerup PV Results
Test
2: Emulation Module Port Feedback Test
Test
3: Run Control FPGA Test
Test
4: Run Control Clock Test
Test
5: Break In and Trigger Out SMB Feedback Test
Test
6: Target Board Adapter Feedback Test (FACTORY ONLY) Not Executed
FAILED
Number of tests: 1
Copyright (c) Agilent Technologies, Inc. 1999
All Rights Reserved.
prior
written permission is prohibited, except as allowed under copyright laws.
HPE8130A Series Emulation System
Version:
A.01.00 Dec 30 1999
Location:
Generics
HP E3454A
PowerPC 700 JTAG Emulator
Version:
A.05.00 Oct 26 1999
R>
The product numbers and version information will be different for your
emulation probe. The product numbers displayed are for the various
pieces of firmware and will be different from the product number you
used to order the product.

If a performance verification test fails

There are some things you can do if a failure is found on one of the tests.
Details of the failure can be obtained through using a -v value ("verbose
level") of 9.
,I WKH SDUWLFXODU IDLOXUH \RX VHH LV QRW OLVWHG EHORZ FRQWDFW $JLOHQW 7HFKQRORJLHV IRU DVVLVWDQFH
Test 1: Powerup PV Results
Failure of this test indicates a hardware problem with the emulation probe.
E5900B / E5901B User's Guide Supplement
Number of failures: 0
Reproduction, adaptation, or translation without
Troubleshooting the Emulator
Problems with the Emulation Probe
Passed!
Passed!
Passed!
Passed!
Passed!
105

Advertisement

Table of Contents
loading

This manual is also suitable for:

E5901b

Table of Contents