Work without voltage
It is essential to carry out the following steps in order to successfully perform the
required tests:
1.
Disconnect the installation from its source.
2.
Check for absence of voltage.
3.
Test preparation by placing all the necessary measuring instruments and closing
the doors totally or partially (as much as possible).
4.
Energise the installation.
5.
Performance of tests making the necessary readings and checks on the tests
STAYING OUTSIDE THE 70 CM PROXIMITY DISTANCE.
6.
Lock the installation so that no one authorised has access to the inside part.
Live working
The tests must only be carried out when it is not possible to apply the previous protocol,
only when it is essential to make connections/disconnections with the equipment
connected.
Beforehand, an analysis of the entire installation in which work have to be done must
be carried out in order to protect all live parts with polycarbonates.
It is important that the protective polycarbonate must always be installed after the
connection has been made.
Insulating tools must always be used.
Tests MUST be stopped in case of rain, wind or
thunderstorm.