394 Chapter 39 Hardware procedures
Powering up a Multiservice Switch 7440
Prerequisites
Procedure steps
NN10600-175 6.1S2
Power up a Nortel Networks Multiservice Switch 7440 after installing all
hardware and cabling.
CAUTION
Risk of equipment damage
You can damage equipment if you power up a device
before you have met the prerequisites listed in
"Prerequisites" (page 399)
•
install cabinet or device shelving
•
install cooling unit equipment
•
install power supplies (in standby mode)
•
install termination panels, if required
•
install customer-equipment cables, if required
•
install control processors (CP) and function processors (FP) in the
disengaged position
•
install card cables
•
install power cords
•
install external alarm cables (for cabinet installations only)
1
Connect and wear the antistatic wrist strap.
2
Make sure that all power supply controls are in the standby position. See
the figure "Multiservice Switch 7440 power supply" (page 396).
3
Ensure that the CP in slot 0 and all FPs are engaged.
4
Toggle on the circuit breakers for the outlets that supply power to the
device.
5
Verify that the LEDs on all power supplies are red.
6
Apply power to one of the power supplies by toggling its power control to
the on position. See "Multiservice Switch 7440 power supply" (page 396).