Powering down a BIM

Prerequisites
Passport 15000, 20000 Hardware Installation, Maintenance, and Upgrade
Power down a BIM to accommodate safe activities involving any hardware or
cables that are connected to it.
CAUTION
Service interruption from power interruption
Switching off the BIP means that the one or two switches
cannot operate. To minimize the impact on traffic of
powering down, choose a period of lowest average traffic
for the affected nodes.
WARNING
Risk of injury or damage by electricity
When switching off power breakers on a breaker interface
module (BIM) or in the circuit up to it, or removing a fuse
from the circuit up to it, always put tape over the breaker
or fuse cavity. The tape indicates it was manually switched
off, and not tripped by the system. This prevents
accidental activation of the power circuit, especially if
power cables are being handled.
WARNUNG
Schäden oder Verletzungen durch Elektrizität
Wenn die Leistungstrennschalter an einem
Trennschalterkopplungsmodul (BIM) oder im
zuführenden Stromkreis geöffnet bzw. Sicherungen aus
dem Stromkreis entfernt werden, decken Sie den
Trennschalter oder den Sicherungssteckplatz mit
Klebeband ab. Das Klebeband signalisiert, daß er/sie
manuell ausgeschaltet und nicht vom System ausgelöst
wurde. Damit verhindern Sie eine versehentliche
Aktivierung der Stromversorgung, besonders beim
Hantieren mit Netzkabeln.