3.5. Securing the Power Cabinet to the Battery Cabinet

1
Battery Cabinet
4
M5 Wavy Washer
1. Place the Power Cabinet on top of the Battery Cabinet.
Note. Either a 2 man lift or mechanical aids rated in excess of 45kg are required for lifting the
Power Cabinet.
2. Secure the Power Cabinet to the Battery Cabinet using the Power Cabinet to Battery Cabinet
Fixings (M5x16 Pozi-drive Pan Head Screw, M5 Wavy Washer and M5 Plain Washer), in 4
positions.
3. Tighten the Power Cabinet to Battery Cabinet Fixings to a torque of 2.9Nm.
Copyright © 2008-2009 Eaton Corporation. All Rights Reserved
2
Power Cabinet
5
M5 Plain Washer.
Fig. 3-9 Securing the Power Cabinet to the Battery Cabinet
Document No: - 4493-CM-EN-10989402
Flexi -3G Installation & Commissioning Manual
Chapter 3. Installation Procedure
2
1
3
Power Cabinet to Battery
Cabinet Fixings
5
4
3
Page 31 of 94

Advertisement

loading