Ac Connection Information; Installing Rectifiers In A Pba-03 System To Balance Phases - Eaton Flexi-3G Installation & Commissioning Manual

Advertisement

1Ø+N+PE (A&B Feeds)
3 core cable of 10mm² minimum
or
10mm² minimum PVC (80°C minimum)
singles in trucking or conduit.

6.6.2. AC Connection Information

6.6.3. Installing Rectifiers in a PBA-03 System to Balance Phases

In order to provide a balanced load on the incoming AC supply, Install the quantity of rectifiers
required for the Power Supply Unit, with reference to the General Notes for Installing a Rectifier in
section 5.2. on page 49 and according to the table below.
AC Input
Terminals
A
B
Table 6-6 Installing Rectifiers in a PBA-03 Power Supply Unit
Copyright © 2008-2009 Eaton Corporation. All Rights Reserved
Table 6-5 PBA-03 Cable Rating
Fig. 6-9 PBA-03 AC Rating Information Label
Phase Connected
Rectifier Position in
To
Cabinet from Left to
Ø1
Ø2
Ø3
Ø1
Ø2
Ø3
Document No: - 4493-CM-EN-10989402
Flexi -3G Installation & Commissioning Manual
Chapter 6. Installation of AC Cables
3Ø+N+PE (A&B Feeds)
5 core cable of 6mm² minimum
or
6mm² minimum PVC (80°C minimum)
singles in trucking or conduit.
Installation Sequence
Right
1
2
3
4
5
6
7
8
9
1
7
2
3
4
5
8
6
9
Page 61 of 94