Loading The Battery Shelves; Checking The Batteries - Eaton Flexi-3G Installation & Commissioning Manual

Advertisement

Flexi -3G Installation & Commissioning Manual
Chapter 4. Battery Installation

4.3. Loading the Battery Shelves

5
4
3
2
1
Battery Cabinet
4
Battery Shelf 3 (Optional)
For stability when placing the Power Cabinet onto the Battery Cabinet, it is essential to secure the
Battery Cabinet to the floor. See section 3.4. Securing the Battery Cabinet on page 30.
Batteries must be loaded into the Battery Cabinet starting with Battery Shelf 1 (Bottom Shelf). This is
to ensure that the Battery Cabinet remains stable.

4.4. Checking the Batteries

1. Check each battery for physical damage.
2. Check that the Terminal Adaptor to Battery Fixings on each battery are tight
3. Measure the open circuit voltage of each battery.
4. Reject any batteries that are damaged or faulty.
Page 38 of 94
2
Batteries placed on Battery
Shelf 1
5
Battery Shelf 4 (Optional)
Fig. 4-2 Battery Cabinets with 4and 5 Shelves of Batteries
Document No: - 4493-CM-EN-10989402
Copyright © 2008-2009 Eaton Corporation. All Rights Reserved
6
1
3
Batteries placed on Battery
Shelf 2
6
Battery Shelf 5 (Optional)