Chapter 1. Floor Marking; Introduction; Standard Terms - C-DOT DSS MAX-XL Installation Manual

Table of Contents

Advertisement

1.1.

INTRODUCTION

As a first step towards the installation of Exchange equipment (iron work, IOP-
PDP), the floor should be marked as per the exchange layout. Floor markings are
done in Switch Room where the main switching equipment is placed and IOP Room
where the input output processors with consoles are placed. The main aim of this
marking is to locate the exact position of the grouting holes which are used for
fixing the equipment in the respective rooms. This chapter covers the materials and
tools required and the detailed marking procedure. However, before carrying out
the floor marking, certain standard terms need to be understood and are therefore
defined.
1.2.

STANDARD TERMS

1.2.1.
Floor
Floor means the normal floor covered with suitable antistatic material.
1.2.2.
Datum Line
A datum line is a straight line drawn through the maximum no. of points
located at a distance, say D, from the wall of the Switch Room/IOP Room.
1.2.3.
Reference Point
It is a point on the Switch Room/IOP Room floor to which the datum lines
and subsequent measurements are related. It is also defined as the
intersection point of the two datum lines drawn at right angles to each other.
1.2.4.
Suite End Line
This is the line drawn parallel to one of the datum line from which the suite
will begin or start growing.
INSTALLATION MANUAL
Chapter 1.
Floor Marking
9

Advertisement

Table of Contents
loading

Related Products for C-DOT DSS MAX-XL

Table of Contents