13. Connect the cables to the controller.
14. Install the primary PCI riser cage.
15. Connect the cables to the backplane:
•
4 LFF
8 SFF
•
16. To enable HPE Smart Array SR SmartCache in a Smart Array P-class Gen10 controller, install an energy pack.
SmartCache and CacheCade enable solid-state drives to be used as caching devices for hard drive media. These
features accelerate access to frequently used data by caching hot data from the hard drives onto the solid-state
drives.
17. Install the access panel.
18. Install the server into the rack.
19. Connect all peripheral cables to the server.
20. Connect each power cord to the server.
21. Connect each power cord to the power source.
22. Power up the server.
23. If removed, install the bezel.
24. Configure the storage controller.
The installation is complete.
Configuring an HPE Smart Array Gen10 controller
Procedure
1. Power up the server.
2. If you are running the server in UEFI Boot Mode, select the boot options.
Hardware options installation
77