Installing a two-bay SFF enablement kit

Prerequisites
Before you perform this procedure, make sure that you have the following items available:
T-10 Torx screwdriver
The appropriate cables needed for the installation. For more information, see cabling.
2 SFF drives or blanks.
Procedure
1.
Back up all server data.
2.
If installed, remove the front bezel.
3.
Power down the server.
4.
Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
5.
Disconnect all peripheral cables from the server.
6.
Do one of the following:
Extend the server from the rack.
Remove the server from the rack.
7.
Remove the access panel.
8.
Remove the universal media bay blank.