42 General Maintenance
Figure 3-16
Variation #3
T-Track
7.
Inspect the packer tunnel for wear. The packer tunnel is considered a wear item and will need to
be rebuilt and/or reinforced periodically to prevent further damage to the packer.
a. Inspect all welds for wear and/or cracks where the cap is attached to the tunnel.
If welds are worn or cracked, they should be ground out and re-welded.
b. Inspect the bend radius on the top and both sides of the tunnel for wear and/or cracks.
If cracked or worn through, the tunnel will need a wear plate overlay installed.
Central Trolley