Installation
48
3.4

Post-installation check

Perform the following checks after installing the measuring device in the pipe:
Device condition/specifications
Is the device damaged (visual inspection)?
Does the device correspond to specifications at the measuring point, including
process temperature and pressure, ambient temperature, minimum fluid
conductivity, measuring range, etc.?
Installation
Does the arrow on the sensor nameplate match the direction of flow through the
pipe?
Is the position of the measuring electrode plane correct?
Is the position of the Empty Pipe Detection (EPD) electrode correct?
Were all screws tightened to the specified torques when the sensor was installed?
Were the correct seals installed (type, material, installation)?
Are the measuring point number and labeling correct (visual inspection)?
Process environment/process conditions
Are the inlet and outlet runs respected?
Is the measuring device protected against moisture and direct sunlight?
Is the sensor adequately protected against vibration (attachment, support)?
Proline Promag 53 PROFIBUS DP/PA
Notes
-
→ Page 162 ff.
Notes
-
level?
→ Page 19
→ Chap. 3.3
Promag W→ Page 28
Promag P→ Page 35
Promag H→ Page 41
-
Notes
Inlet run: ≥ 5 x DN
Outlet run: ≥ 2 x DN
-
Acceleration up to 2 g by
analogy with IEC 600 68-2-6
→ Page 166
Endress+Hauser

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the PROFI BUS Proline Promag 53 PROFIBUS DP and is the answer not in the manual?

Subscribe to Our Youtube Channel

This manual is also suitable for:

Profi bus proline promag 53 profibus pa

Table of Contents