4.3 Piping for System 3

IM 11M12A01-02E
Piping in System 3 is illustrated in Figure 4.10. In System 3, calibration is automated;
however, the piping is basically the same as that of System 2. Refer to Section 4.2.
Adjust secondary pressure of both the air set and the zero gas reducing valve so that
these two pressures are approximately the same. The flow rate of zero and span gases
(normally instrument air) are set by a single needle valve.
After installation and wiring, check the calibration contact output (see Sec. 7.11.2), and
adjust zero gas reducing valve and calibration gas needle valve so that zero gas flow is
within the permitted range. Next check span gas calibration contact output and adjust
air set so that span gas flow is within the permitted range.
CHECK
OUT
flow
meter
*2
EV1
ZERO GAS IN
*2: Needle valve comes with flowmeter
Figure 4.9 ZR40H Autcalinration unit piping diagram
If the contact input to the converter is used for the blow back function, prepare blow
back piping according to Section 4.3.1.
Note
Blow back function means the function to get rid of dust inside a probe in a high-
temperature probe adapter by using compressed air, when a high-temperature detector is
used.
REF
OUT
flow
meter
*2
EV2
AIR IN
Instrument air Approx.
1.5 l/min.
F2.6-3E.EPS
4. Piping
4-9

Advertisement

Table of Contents
loading

This manual is also suitable for:

Zr22gZr402g

Table of Contents