Cart Up/Down Handle Replacement Procedure - GE Venue Go Service Manual

Table of Contents

Advertisement

P R E L I M I N A R Y
D
5813707-100, R
IRECTION
8-2-21

Cart Up/Down Handle Replacement Procedure

8-2-21-1
Tools
Phillips screwdriver of appropriate size
FRU Part #
Table 9-16
Refer to
8-2-21-2
Time Required
5 min
8-2-21-3
Preparations
1.) Shut down the Venue Go™ ultrasound unit, as described in
2.) Prepare stable flat surface covered with a soft material (such as foam) to prevent scratches to the
display.
3.) Dismount Venue Go™ system from cart and place it on a previously prepared surface with the
display facing down.
8-2-21-4
Up/Down Handle Removal Procedure
4.) If ECG is installed in the up/down handle's screws side, remove the ECG
5.) Remove the 3 screws holding the Up/Down handle. .
8-2-21-5
Up/Down Handle Installation Procedure
1) Install the Up/Down Handle on the cart using 3 screws.
2.) If removed, re-install ECG assembly.
2
EVISION
.
on page 9-17
ECG Removal Procedure
Figure 8-133 Disconnect Up/Down Handle Screws
ECG Installation Procedure
Chapter 8 - Replacement Procedures
V
™ S
ENUE
ERVICE
Power Shutdown
.
M
ANUAL
8-53