Uncrating and Inspecting the Analyzer

The analyzer and its sample system is shipped pre-mounted on a back-
pan, either alone in a crate or in a crated weatherproof shelter. Upon
receiving the analyzer, remove the shipping crate and check the exterior
of the shelter and/or analyzer for damage. Open the shelter and verify its
internal components are secure and there is no physical damage.
Remove the M10 screw from the analyzer's Electronics Enclosure and
open the enclosure. Verify its internal components and wiring are secure
and there is no physical damage.
The Heatsink/Measuring Cell Assembly is shipped in a separate box. Re-
move the shipping crate and check it for any physical damage.
!
Avoid damaging the analyzer's piping and instrumentation by lifting
it out of its shipping crate using only its backpan. DO NOT use any
CAUTION
piping or instrument to lift.
!
The analyzer and its backpan weighs approximately 60 kg (132 lb).
Use caution when lifting it from its crate.
WARNING
!
After the inspection, use a soft, non-abrasive cloth to gently clean the
joining areas (flamepaths) of the enclosure and its door. Replace and
CAUTION
tighten at least one M10 screw (if installing immediately) – this will
keep the enclosure secure and will prevent damage to the flamepath.
If the Heatsink/Measuring Cell Assembly is not being installed at this
time, store it in its shipping box until it will be installed.
Installation and Start-Up
|