Chapter 5. Installing the Modules and Initially Starting the System
This document is property of Emerson Network Power, Energy Systems, North America, Inc. and contains confidential and proprietary information owned by Emerson Network Power, Energy
Systems, North America, Inc. Any copying, use, or disclosure of it without the written permission of Emerson Network Power, Energy Systems, North America, Inc. is strictly prohibited.
4) When initialization is complete, the Main screen displays voltage and current
normally, and no alarms are active.
5) System information is displayed in multiple screens. Repetitively press the up or
down arrow key to view other system information screens one by one.
6) From the Main screen, press ENT to go to the "Main Menu" screen.
7) From the Main Menu, select a submenu by repetitively pressing the up or down
arrow key. The selected submenu will be indicated by the cursor. Press ENT to
open the submenu.
Note: Repeatedly press the "ESC" key to return in reverse order level by level from
any submenu until the Main screen appears.
8) Verify and set the ACU+ controller as required for your application. Refer to the
ACU+ User Instructions (UM1M820BNA) for procedures. Note that you will have
to program the ACU+ for any temperature probes and external inputs/outputs
connected to the IB2 Interface Board, optional EIB Interface Board, and optional
SM-DU+ Shunt Interface Board.