Step 2 Remove cables from the BIM panel, and remove the BIM from the corresponding battery.
Figure 5-54 Removing a BIM
The battery appearance is for reference only.
Step 3 Secure the new BIM on the fastener, and connect the BIM cables.
Verify that the BIM network parameters are cleared.
Step 4 Press the networking switch on the BIM for 2 seconds based on the battery number
corresponding to the new BIM. When the RUN/ALM indicator turns from steady red to
blinking green at super short intervals, and finally to blinking green at long intervals, the BIM
connects to the CIM network.
Step 5 After checking that the BIM networking is complete, set the blinking function. If the BIM
blinks successfully, the installation succeeds. If the BIM fails in blinking, check the cable
connections and reinstall the BIM.
After the blinking succeeds, set BIM stop blinking, select the battery number from the range of 1–300,
and click Submit to stop the blinking.
Issue 01 (2019-03-05)
On the CIM WebUI home page, choose Monitoring > CIM System > Running Control,
set BIM start blinking, select the corresponding battery numbers 1–300, and then click
Submit.
Figure 5-55 Setting the BIM blinking function on the CIM WebUI
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
5 Parts Replacement
157

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r001

Table of Contents