Figure 5-1 Remove the protective panel
Step 2 Switch off the SPD circuit breaker.
Step 3 Detect the L1, L2, L3, and N voltages to the PE using an electrical tester pen, and verify that
the faulty SPD has no voltage before replacing the faulty SPD.
detect the voltages.
Figure 5-2 Detecting the voltages
Step 4 Hold the faulty SPD and pull it out.